In the roadmap plan, the item that I plan is limited to the timeline that is set. Example if as per my timeline I have set length of the period as 1 month then all the items that I plan are shown within that 1 month. If there are items that span for more than 1 month, then is there any way to show the item box to all the aplicable months instead of creating a new item for each month.
by: Seeja J. | over a year ago | User Interface
Comments
As of the Summer 2016 release, roadmaps can be viewed as a board, which shows the delivery period, or a timeline, which shows the total duration of the work. The same roadmap can be toggled between these views.